TMI Coatings, LLC (TMI) was contracted by a highway/heavy construction company to perform comprehensive pipe painting services for the Met Council, including surface preparation and coating of large diameter underground piping (over 100’ below grade) and support stands. Since the project required working in a confined space, we had to ensure all safety protocols were continuously followed to maintain safety for all team members.
Project Details:
- TMI Coatings provided and mobilized all the necessary equipment, tools, and resources to ensure the project was completed efficiently and to the highest standards. This included a material lifting hoist, scaffolding, forklift, construction trailers, temporary power, a gooseneck trailer with 2- 825 air compressors, and a sand pot.
- Given the nature of the work environment, TMI adhered strictly to all safety regulations and confined space entry procedures. This included the use of proper ventilation, air monitoring, and personnel safety measures to ensure a safe working atmosphere throughout the project.
- After scaffolding erection, protection measures were implemented to prevent sand blast media and dust from seeping into undesirable places and to prevent paint drips and splatter. TMI built and utilized a temporary containment underground.
- TMI executed pressure washing as required to remove contaminants such as grease, oil, dirt, and grime from the pipes and surrounding areas.
- TMI then performed sandblasting in compliance with the standards set forth by the Association for Materials Protection and Performance (AMPP). This critical step ensured proper surface preparation by effectively removing rust, old coatings, and other debris, providing a suitable profile for the new coating system. Unfortunately, water intrusion stopped our work multiple times requiring us to vacate the area for the owner to perform weld repairs. After work was completed TMI was required to re-mobilize to the site, re-wash, re-blast and resume painting.
- Samples of abrasives were collected and a TCLP test was performed prior to TMI disposing of the spent abrasive as specified.
- TMI applied one full prime coat of PPG Amerlock 2 @ 4 – 8 mils DFT, an intermediate coat of Pitthane Ultra @ 2 – 3 mils DFT and a topcoat of Pitthane Ultra @ 2 – 3 mils DFT.
Conclusion:
TMI successfully completed the pipe painting project for the construction company while meeting all technical and safety requirements. TMI ensured a durable and high-quality coating solution for the underground piping and support structures.